Ask the isolator supplier for a delivery package description and the proposed schedule. Identify who arranges receiving and who coordinates the supplier’s arrival with other site contractors. Record which visit or support activity is included in the equipment price.
Budget separately for what happens if delivery changes
Request the terms for rescheduling, storage and additional attendance. Give the warehouse and project contacts the agreed equipment and purchase references and record who can approve a change.